Renovations

Guides

Purple floral wallpaper, ornate gold oval mirror and navy floating vanity above a black hexagon floor

Renovation budgeting

How to set a renovation budget and contingency

Set a renovation budget by starting from the most you can spend in total and working backwards: take out 13% HST, then hold back a contingency of 10% to 20% depending on the house, and design to what is left. Builders Ontario suggests 10% for a standard kitchen, 15% for a house built before 1980 and 20% or more for renovating an older house; HomeStars recommends 15% to 20%. Keep the contingency in your own account, not inside the contract price.

By the Purple Kitchen & Bath team · Updated · 4 min read · Photo: a Purple Properties project

Work backwards from the total you can spend

Many first budgets start from a contractor's price and add tax and surprises afterwards. Reverse the order: fix the all-in ceiling first, from savings plus whatever financing you qualify for, then divide down to the number you design to.

The design budget is your ceiling divided by 1.13 for HST, then by one plus your contingency rate. At a 15% reserve, $90,000 all-in leaves about $69,260 to design to, roughly 77% of the ceiling. That is the figure to give a designer or contractor at the first meeting. Because the tax comes out first, any reserve you end up spending already has its HST covered.

Working back from an all-in ceiling with a 15% contingency. Calculated; HST at Ontario's 13% rate (Canada Revenue Agency).
All-in ceilingAfter 13% HSTContingency held backBudget to design to
$50,000$44,248$5,771$38,476
$90,000$79,646$10,389$69,257
$150,000$132,743$17,314$115,429

How big the contingency should be

Size the reserve by how much is still unknown. The age of the house, how complete the drawings are, and whether walls or plumbing move all push it up.

The last row is not true contingency. When finishes are still allowances, the reserve is covering the unpriced part of the job, so making selections before you sign lets you hold less; choosing renovation finishes without delays shows how to get there.

Contingency guidance from Ontario and Toronto sources, 2026.
SituationReserveSource
Standard kitchen, house built after 1980, drawings complete10%Builders Ontario, kitchen cost guide
Kitchen in a house built before 198015%Builders Ontario, kitchen cost guide
Toronto renovations in general15% to 20%HomeStars
Renovation or addition on an older house20% or moreBuilders Ontario, contingency guide
Drawings unfinished, or allowances carrying much of the price20%Builders Ontario, contingency guide

What older GTA houses reveal once the walls are open

A contingency exists for what nobody can see before demolition. In older houses the usual findings are wiring, electrical service, hazardous materials and floors, and most have published Ontario prices.

One finding can use up a 10% reserve on its own: a panel upgrade at Builders Ontario's $3,800 default is close to 10% of a $40,000 kitchen. That is the case for 15% or more in a pre-1980 house. Old house surprises behind the walls and asbestos and lead in older homes go deeper.

Common findings in older houses and published costs, before HST. Sources: Builders Ontario rewiring and subfloor guides (checked October 2026) and Health Canada.
FindingWhere it turns upPublished cost
Aluminum branch wiringHouses built from the mid-1960s to the late 1970sPigtailing at $40 to $100 per point; $2,000 to $6,000 for a typical house
Knob-and-tube wiringOlder houses; many insurers want it inspected or replaced$12,000 to $25,000 to replace in a 1,500 to 2,500 sq ft house, panel included
A 100 A service too small for new circuitsOlder houses adding induction, wall ovens or heated floors$2,500 to $5,000 for a 200 A upgrade with overhead service; Toronto Hydro charges $120 to disconnect and reconnect
Possible asbestosPlaster, floor tiles, drywall compounds and pipe insulation from before 1990No reliable published price; Health Canada advises testing before renovating and a qualified removal specialist if found
Rotted subfloorAt toilets, dishwashers and patio doorsAbout $6 per sq ft of sheathing replaced
Floor out of levelSagging joists or wavy subfloor under new tileAbout $3 per sq ft of self-levelling compound at 1/4 in.

Keep the reserve outside the contract and release it by change order

Builders Ontario's contingency guide puts it bluntly: a contingency inside the builder's price is just a higher price. Hold it in your own account, show it as its own line in any budget a lender sees, and release it only through a written change order for a documented surprise.

  • It pays for conditions nobody could see: rot under a toilet, wiring that fails inspection, a code change between drawings and permit, a supplier that fails to deliver.
  • It does not pay for upgrades or changes of mind. Fund those by cutting elsewhere or with new money, or the reserve is gone before the walls are closed.
  • Allowances are not contingency. An allowance is a placeholder inside the price for something not yet chosen; picking above it is an upgrade, priced as a change order. See renovation change orders and renovation contracts in Ontario.

Costs that sit outside the contractor's estimate

A renovation budget covers more than the contract. Before you fix the design number, list everything else that will come out of the same ceiling.

  • HST at 13% on everything a registered business bills you; see HST on renovations in Ontario.
  • Items you buy yourself, such as appliances or light fixtures, when they are not in the contract.
  • Design fees, if you hire an independent designer.
  • Permit fees, where the work needs a permit. Toronto Building's 2026 schedule has a $214.79 minimum.
  • Living costs during the work, such as eating out while the kitchen is closed; living without a kitchen during a renovation has ways to cut them.
  • Financing costs: interest and set-up fees on a line of credit or loan; see renovation financing options in Canada.

Test the number against real scope before design begins

Once you have a design budget, check it against published figures for the scope you have in mind. If $69,000 is the number and the plan calls for a load-bearing wall, a sink moved to the island and built-in appliances, the gap shows now, while it can still be closed by changing the plan rather than cutting finishes mid-build. The kitchen renovation budget breakdown shows how the money divides as the scope grows.

Then rank the wish list into must-haves and nice-to-haves before anyone draws. If the reserve gets spent, the nice-to-have list is where money comes back from, decided calmly in advance instead of with the walls open.

Questions

What happens to the contingency if nothing goes wrong?

If you hold it yourself, it stays yours. That is the main argument for keeping it out of the contract: an unused reserve built into a fixed price is simply paid to the contractor.

Should I tell my contractor my real budget?

Give the design budget, after HST and the reserve. A contractor who knows the real number can steer layout, cabinet grade and finishes to fit it, instead of pricing a project you will have to cut back later.

Does contingency spending carry HST?

Yes. Extra work billed by a GST/HST-registered contractor is taxed at 13% like the rest of the contract. Taking HST out of your ceiling before setting the reserve, as above, covers that tax automatically.

How should allowances be written in a quote?

Ask for each allowance in writing with the product, quantity and unit price it assumes, for example tile per square foot or a light fixture each. Then price your actual choices against them before signing, so the allowance is real money rather than a placeholder.

Sources and further reading

  1. Builders Ontario: Construction Contingency, How Much to Hold Back (2026)
  2. Builders Ontario: Kitchen Renovation Cost in Ontario (2026)
  3. Builders Ontario: Cost to Rewire a House in Ontario (2026)
  4. Health Canada: Asbestos and your health
  5. HomeStars: How Much Do Renovations Cost in Toronto in 2026?

Checked November 19, 2026. Codes, by-laws, prices and product specifications change; confirm with your municipality, condo corporation or supplier before you build.

Plan your kitchen renovation

Initial consultations are complimentary. Jordan Duda, our client care and lead estimator, is usually your first point of contact.