Choosing renovation finishes without delays

Finishes hold up renovations when they are chosen in showroom order instead of build order. Decide each item before the trade that depends on it starts: valves and vanities before the plumbing rough-in, light fixtures before wiring, sinks before countertop templating, tile before waterproofing. Approve samples from the lot you will actually receive, confirm stock and delivery dates in writing, and have every item on site and checked before its install week.

By the Purple Kitchen & Bath team · Updated · 5 min read · Photo: a Purple Properties project

Decide each finish before the stage that depends on it

Every finish has a deadline set by the trade that has to build around it, and that deadline is usually earlier than homeowners expect. A faucet seems like a last-week purchase, but a wall-mounted one fixes the valve depth in week two. Plot your choices against the build, not against the order you'd shop for them.

The table works for a kitchen and a bathroom alike. Items near the top are needed earliest; the kitchen renovation checklist and bathroom renovation checklist list the dimensions to confirm for each.

Decide-by points for common finishes
FinishDecide beforeBecause
AppliancesThe cabinet orderCabinets are built to each appliance's cut-out and connections
Cabinet style, finish and hardware sizeThe cabinet orderDoor construction, finish and drilling are set in production
Shower valve, trim and wall-mounted faucetsPlumbing rough-inThe valve body goes into the wall before it closes
Vanity, sinks, toilet and tubPlumbing rough-inDrain and supply positions are fixed to the chosen models
Light fixtures, fan and floor heatingElectrical rough-inBox positions, blocking and circuits follow the fixtures
Countertop material and slabsCabinet installationSlabs must be reserved before the template visit
Sink, faucet and cooktop modelsTemplate dayCut-outs and faucet holes are made in the shop
Tile, trims, grout colour and layoutWaterproofing and boardTrims and niche sizes depend on the tile; quantities need ordering
Shower glass style and hardwareTileBlocking and curb details depend on it, even though glass is measured last
Paint colours and sheensDrywall finishingQuick to buy, but primer and colour are the next step

Approve samples from the lot you will actually receive

A showroom sample is a promise about a product line, not about the boxes delivered to your house. Tile is made in production runs that can differ slightly in shade, natural stone varies slab to slab, and Daltile notes that even grout colour can vary from batch to batch.

Before you approve, ask for a sample from current stock, or a photo of the actual lot with its shade and lot numbers. For natural stone, view your own slabs: Daltile recommends viewing natural stone with your installer before installation, and quartzite countertops explains the tests worth running on a stone sample before you commit.

Record each approval with the product code, finish code, lot number where there is one, and a photo. When a cabinet door finish or a faucet in brushed gold arrives a shade off, that record turns an argument into a quick exchange.

Order enough, and order it together

Running short of tile in the last week is one of the most avoidable delays in a renovation. Daltile recommends buying about 10% more tile than you expect to need and keeping attic stock from the same dye lot, because a reorder months later may not match.

Herringbone, diagonal layouts and small rooms with many cuts use more than a straight lay, so ask your installer for the overage on your specific layout. Order all of one tile at once, and have the installer mix tiles from different boxes as they go, which Daltile also advises for an even result.

  • Tile and trims for every room in one order, from one lot.
  • Spare cabinet door and drawer front in the same finish, if the maker offers one.
  • Grout and sealant from one batch for each colour.
  • Extra flooring boxes kept for repairs.
  • Paint colour formulas written down, with sheen and brand.

Treat 'in stock' as a claim to confirm

A product listed as available may be in a warehouse in another province, on a container, or one of the last few units. Before an order is placed, ask for the confirmed ship date, the warehouse it ships from, and an order acknowledgement listing the exact model and finish codes. Custom items, from cabinets to vanities to shower glass, have production times that start only once drawings are approved; kitchen cabinet lead times and ordering covers the biggest one.

If you buy items yourself, the delivery date in your agreement carries weight. Under section 26 of Ontario's Consumer Protection Act, 2002, a consumer may cancel a future performance agreement before delivery if the supplier doesn't deliver within 30 days after the delivery date in the agreement, or an amended date the consumer agreed to in writing. If you accept delivery after that period has passed, you can no longer cancel under that section. Ontario has passed a new Consumer Protection Act, 2023, which replaces the 2002 Act on a date to be proclaimed, so check the current rules if you rely on them.

When something is backordered, decide fast

A backorder found early is a choice; found on install day, it is a delay. As soon as an item slips, compare three options against the schedule.

Responding to a backordered finish
OptionWorks whenWatch for
Wait for the originalIt is installed late in the build, such as hardware, mirrors or light trimsMake sure nothing earlier depends on its exact size
Choose a pre-approved alternateYou picked a second choice during designRough-in dimensions, finish match and trim compatibility
Resequence the workOther rooms or stages can move aheadInspections and cure times that can't move
Install a temporary pieceA toilet, faucet or light is needed to use the roomPaying to install twice

Check deliveries the day they arrive, and store them properly

Finishes should be on site and inspected before their install week, not opened on the morning they're needed. Open every carton, compare model numbers, finish codes, quantities and lot numbers against the order, and photograph any damage before signing or within the supplier's reporting window.

Store materials where they will be installed, or somewhere as close to those conditions as you can. MAPEI's grout data sheet calls for dry, heated storage on site and delivery at least 24 hours before tilework begins. Keep cabinets and wood flooring out of damp garages, and leave appliances boxed and protected until the crew is ready for them.

Finally, agree in the contract who orders what. Owner-supplied items need a delivery deadline, a named person to check them, and a clear rule on who handles damage and returns; renovation contracts in Ontario covers the wording.

Questions

How much extra tile should I order for a renovation?

Daltile recommends about 10% more than you expect to need, kept as attic stock from the same dye lot. Patterns with many cuts, such as herringbone, can need more, so ask your installer to calculate it for your layout.

Can I supply my own fixtures and appliances?

Usually, if it is agreed up front. Settle the delivery deadline, who checks each item on arrival, and who is responsible if something is damaged or the wrong size, and give the contractor the specification sheets early.

What if my tile is discontinued in the middle of the project?

That is the reason to buy every piece, plus overage, in one order before work starts. If it happens anyway, choose a replacement for a whole surface rather than mixing old and new on one wall.

Do all finishes need to be on site before demolition?

Not all of them, but every long-lead item should be ordered and confirmed, and anything needed at rough-in, such as the shower valve and vanity, should be on site or have final specifications by then.

Sources and further reading

  1. Daltile FAQs: ordering extra tile, attic stock and natural stone
  2. Consumer Protection Act, 2002, s. 26 (late delivery), Ontario e-Laws
  3. Keracolor S technical data sheet (MAPEI Canada)

Checked November 19, 2026. Codes, by-laws, prices and product specifications change; confirm with your municipality, condo corporation or supplier before you build.