Renovation process

What happens during a kitchen renovation, week by week

A kitchen renovation runs in a fixed order: protection and demolition, rough-ins and inspections, drywall, cabinets, countertop templating and fabrication, then backsplash, appliances and a final walkthrough. Purple Kitchen & Bath puts most GTA renovations at 6 to 16+ weeks. The nine-week example below follows a kitchen that keeps its footprint but moves the sink and adds circuits, showing what you will see, hear and be asked to decide each week.

By the Purple Kitchen & Bath team · Updated · 5 min read · Photo: a Purple Properties project

Before week one, most of the kitchen is already decided

The first day on site is the visible start of work that began weeks earlier. By then the layout and selections are final, cabinets are in production, and any building permit has been issued. The electrical side has its own paperwork: the Electrical Safety Authority (ESA) requires whoever does the wiring to file a notification of work before starting.

Your jobs in the final days are practical: empty the cabinets, set up a temporary kitchen, and agree where the crew will enter, park and stage materials. The stretch before demolition, and why cabinets usually set its length, is covered in how long a kitchen renovation takes.

A nine-week kitchen, as the homeowner lives it

This is an illustration, not a schedule promise. A kitchen with a wall removal, custom millwork or surprises behind the plaster takes longer, and a straight replacement can be quicker. The order, though, rarely changes.

Example: a mid-size kitchen with a relocated sink and new circuits
WeekWhat happens on siteWhat you noticeWhat you're asked
1Floors and doorways protected, dust walls up, old cabinets, counters and flooring removedThe loudest week; a bin on the driveway; water or power off for short spellsConfirm what is being kept or salvaged
2Framing fixes, new plumbing for the sink, new circuits and boxes, hood ductOpen walls and trades coming and goingWalk the rough-in and check every box against the plan
3City plumbing rough-in inspection, ESA rough-in inspection, then insulationDays with little visible progressGive inspectors access; nothing gets covered yet
4Drywall hung, taped, sanded and primedFine dust and a primer smellFinal paint colours
5Cabinets delivered, set, levelled and fastened; panels and fillers fittedIt finally looks like a kitchenCheck door gaps and hardware positions
6Countertop template, then fabrication in the shopA quiet week with no counters or sinkBe home for the template and approve seams and overhangs
7Counters installed; sink, faucet and dishwasher connected; devices installedRunning water returns to the kitchenLook over the stone before the installers leave
8Backsplash tile and grout, appliances, hood, light trims, touch-upsWet saw noise, then grout hazeApprove grout colour; check each appliance
9Final inspections, deficiency fixes, cleaning, walkthroughTrades finishing small itemsWalk through, sign off, collect manuals and warranties

Demolition week sets the tone for noise and dust

Week one is the hardest on a household. In Toronto, the noise by-law bars clearly audible construction noise from 7 p.m. to 7 a.m. on weekdays, before 9 a.m. on Saturdays, and all day on Sundays and statutory holidays, so expect the loud work inside those hours.

Dust walls, sealed doorways and covered floors along the crew's route do most of the protecting; renovation dust control explains the options. In a house built before 1990, the materials coming out should be tested before this week starts, not during it; see asbestos and lead in older homes.

Demolition is also when hidden conditions show up: old wiring, a sagging joist, a drain that can't take a new connection. Any change to scope should come to you in writing with its cost and its effect on the calendar before work continues.

Inspection days decide when the walls can close

The rough-in walk in week two is your best chance to move a receptacle or a pendant box cheaply. Stand where you will chop, check the island receptacle, the under-cabinet light feeds, the hood duct route and the water line for the fridge.

Then the inspectors come. ESA's rough-in inspection happens once branch circuit wiring and boxes are in, and ESA states that no wiring is to be concealed by insulation or drywall until an inspector authorizes it. Where a City permit applies, Toronto Building inspects the plumbing rough-in when it is complete and ready for testing, and framing and insulation stages where walls changed. The City inspects within two business days of a request and warns that work covered before inspection must be uncovered.

That is why week three can look idle. The wait is the system working: walls stay open until each inspector has seen what will be hidden. Building inspections during a Toronto renovation explains each stage.

Midway, the kitchen looks finished before it works

Week five is the morale boost: cabinets in, panels on, the room recognizable. Week six can feel like a stall, because the countertop fabricator measures the installed cabinets and then cuts the stone off site. The sink stays disconnected until the counters are in, so the temporary kitchen keeps working; see living without a kitchen during a renovation.

Use the pause. Confirm where seams fall and how far the island overhang runs (countertop thickness and overhangs), whether a full-height slab backsplash is coming from the same slabs, and that hardware is on site so it can go on as soon as the counters are down.

The last two weeks: tile, appliances and sign-offs

Backsplash tile goes on after the counters, because it has to meet the finished stone. Tile and setting materials should arrive ahead of the tiler; MAPEI's grout data sheet asks for dry, heated storage on site and delivery at least 24 hours before tilework begins. Its Keracolor S grout also needs 21 days to cure fully before regular cleaning, so go easy with cleaners for the first few weeks.

Appliances, the hood, light trims and cover plates go in next. ESA asks for its final inspection once every receptacle, switch, cover plate and fixture is installed and the panel directory is complete, and whoever filed the notification receives the ESA Certificate of Acceptance; ask for a copy. If the City issued a permit, the property owner is responsible for booking the final inspection that closes it.

The walkthrough comes last: test every drawer, door and appliance, run the water, and list anything that needs attention. Renovation punch lists and deficiencies explains how that list gets closed.

Where the weeks stretch

When a kitchen runs past its plan, it is usually for one of a few reasons, and most can be anticipated during design.

  • A failed or rescheduled inspection, which holds the walls open.
  • Something found during demolition that must be fixed first.
  • A late or damaged delivery; choosing renovation finishes without delays covers how to prevent it.
  • A change of mind after an item is ordered, which restarts its lead time.
  • Appliances not on site when the cabinets or counters need them.

Questions

Do I need to be home while my kitchen is being renovated?

Not every day, but stay reachable. The days worth being there for are the start, the rough-in walk, template day and the final walkthrough, because each one ends with a decision that is hard to undo later.

What should I check at the rough-in walkthrough?

Receptacle and switch positions, the island receptacle, pendant boxes centred on the final island, under-cabinet light feeds, the hood duct route, and the dishwasher and fridge water lines. Moving any of them now costs far less than after drywall.

Will the whole house lose water or power during the work?

Only for short periods, when lines are cut, capped or connected and when circuits are added at the panel. Ask the crew to warn you the day before, especially if someone works from home.

What paperwork should I have when the kitchen is done?

The ESA Certificate of Acceptance for the electrical work, proof that any City permit was closed with a final inspection, appliance manuals and registrations, and the contractor's workmanship warranty. Keep them together for your insurer and a future sale.

Sources and further reading

  1. When to call for inspection of small buildings (City of Toronto)
  2. Notifications and inspections (Electrical Safety Authority)
  3. Toronto Municipal Code Chapter 591, Noise (s. 591-2.3 Construction)
  4. Keracolor S technical data sheet (MAPEI Canada)

Checked November 19, 2026. Codes, by-laws, prices and product specifications change; confirm with your municipality, condo corporation or supplier before you build.