Renovation payments
Renovation deposits and payment schedules
Keep a renovation deposit small: Ontario's consumer protection office recommends no more than 10% of the contract price, and never paying the full amount before the work is finished. After the deposit, tie each payment to a milestone you can see, such as passed rough-in inspections or installed cabinets, keep back the 10% holdback the Construction Act requires from every payment, and pay by a traceable method instead of cash.
How much deposit is reasonable
Ontario's guidance is specific: keep down payments to a minimum, with no more than 10% recommended, and never pay the full contract price before the job is done. A deposit is money at risk until work starts. The province's own warning about the 'disappearing contractor' describes large deposits collected 'to pay for materials' for jobs that never begin, and notes that legitimate renovation companies have enough credit to buy the materials they need.
Custom items are the one case where a larger early payment can be reasonable, because cabinets, vanities and stone slabs are made to order for your room. If a contractor asks for more than the deposit to order them, tie that payment to evidence: a supplier order confirmation for your project and an expected delivery date. Pay it when the order is placed, not at signing.
Tie payments to milestones you can see
A good schedule pays for work that has happened. Avoid schedules built only on dates ('week three: 30%'), because if the job slips, date-based payments run ahead of the work. Each progress payment below is 90% of the value of work done in that stage, with 10% held back.
| Milestone | Payment | Check before you pay |
|---|---|---|
| Contract signed | Deposit, ideally no more than 10% | Signed contract, permit plan, insurance and WSIB details |
| Custom orders placed | Materials payment, if agreed | Supplier order confirmation and delivery date |
| Rough-ins complete | Progress payment, less 10% | Plumbing and building inspections passed; ESA notification filed for the electrical work |
| Cabinets, vanity or tile installed | Progress payment, less 10% | Work matches the drawings and selection sheets |
| Substantial completion | Progress payment, less 10% | Room usable; deficiency list written and dated |
| Lien period ends | Holdback released | Lien rights expired and no claim for lien on title |
Keep back 10% from every payment
The holdback is not optional. Under section 22 of Ontario's Construction Act, each payer on a contract under which a lien may arise must retain 10% of the price of the work and materials as they are supplied, and section 24 lets you pay up to 90% without risk unless you have received written notice of a lien. Contractor liens generally expire 60 days after the job is completed or a certificate of substantial performance is published, and the owner then pays the holdback within 14 days.
The Act's prompt payment rules work alongside this. A contractor's proper invoice must be paid within 28 days unless you give a notice of non-payment in the prescribed form within 14 days, but that duty is expressly subject to the holdback. Holdbacks on renovation projects in Ontario walks through the timing with a worked example.
Pay in ways that leave a record
- Cheque, bank transfer or credit card, each matched to a dated invoice that names the same company as your contract.
- Avoid cash. Ontario warns that without a receipt you have no proof of payment if anything goes wrong; if you must pay cash, get a detailed, signed receipt.
- Credit cards carry a statutory backstop. Under section 99 of the Consumer Protection Act, 2002, if you cancel an agreement under the Act, or a payment was taken in breach of it, and the contractor does not refund you, you can ask your card issuer in writing to reverse the charge.
- Financing. If a contractor offers to arrange a loan, Ontario suggests it may be wiser to arrange your own. Compare options in renovation financing options in Canada.
- Keep one folder for the contract, invoices, receipts and signed change orders.
Payment requests that deserve a pause
Most payment disputes start with money moving ahead of the work. Stop and ask questions if a request does not match the schedule you signed, if a deposit well above 10% comes with no custom-order reason, if payment is wanted in a different company's name or a personal account, or if you are asked for the final payment while the deficiency list is still open. A change in scope should arrive as a signed change order with its own price, not as an unexplained increase in the next invoice.
Questions
Why do contractors ask for a deposit at all?
A deposit secures a place in the schedule and covers early costs such as design time, permit applications and the first orders. That is reasonable. The question is size: Ontario's consumer guidance recommends no more than 10%.
Is half up front ever normal for a renovation?
It shifts most of the risk to you before any work is done, and it is far above what Ontario recommends. If a contractor says it needs that much for materials, ask to pay for custom orders when they are placed, against a supplier confirmation, instead of at signing.
Can I pay a renovation deposit by credit card?
If the contractor accepts cards, yes. Beyond the record it creates, section 99 of the Consumer Protection Act lets you ask your card issuer to reverse a charge in specific cases, such as an agreement you validly cancelled where the contractor did not refund you.
When should I make the final payment?
Once the work is substantially complete and the agreed deficiencies are fixed, less the 10% holdback. The holdback follows once lien rights have expired, usually about two months after completion.
Sources and further reading
- Your rights when starting home renovations or repairs, Government of Ontario
- Construction Act, R.S.O. 1990, c. C.30 (Parts I.1 and IV)
- Consumer Protection Act, 2002, section 99 (credit card charge-backs)
Checked November 19, 2026. Codes, by-laws, prices and product specifications change; confirm with your municipality, condo corporation or supplier before you build.