Renovations

Guides

Renovation crew on a site walkthrough in a newly opened-up space

Renovation payments

Holdbacks on renovation projects in Ontario

On an Ontario renovation, the Construction Act requires you, as the owner, to keep back 10% of the value of the work and materials as they are supplied, from every payment. You release it once lien rights have expired, generally 60 days after the job is completed or a certificate of substantial performance is published, and pay it within 14 days after that. Keeping it caps your exposure if the contractor leaves a subcontractor or supplier unpaid.

By the Purple Kitchen & Bath team · Updated · 4 min read · Photo: a Purple Properties project

Why a homeowner has to hold back money at all

The holdback exists because of liens. Under the Construction Act, anyone who supplies work or materials to an improvement can claim a lien against the property if they are not paid, and the Act defines an improvement to include any alteration, addition or capital repair to land. A new kitchen or bathroom qualifies. If your contractor fails to pay its tile setter or cabinet supplier, that firm can register a claim for lien on your title, even if you paid the contractor in full.

Section 22 answers that risk. Each payer on a contract under which a lien may arise must retain 10% of the price of the services or materials as they are actually supplied, whether the contract provides for progress payments or a single payment on completion. In return, section 23 caps an owner's personal liability to lien claimants at the holdback the owner was required to keep. Pay 100% early, and you may end up paying that 10% twice.

A worked example on a $90,000 kitchen

The numbers below apply the Act's rules to a $90,000 kitchen contract that is completed on March 2. Dates and amounts are illustrative; your contract and your lawyer settle the details.

Construction Act holdback rules applied to a $90,000 renovation
ItemRuleOn a $90,000 contract
Basic holdback10% of work and materials supplied (s. 22(1))$9,000 retained by the end of the job
Each progress paymentPay up to 90% of value supplied, unless you have written notice of a lien (s. 24)A $30,000 stage is paid as $27,000
Substantial performanceReady for use, and the cost to finish or fix known defects is no more than 3% of the first $1 million (s. 2(1))Remaining work worth $2,700 or less
Deemed completionCost to finish is no more than the lesser of 1% of the price and $5,000 (s. 2(3))Remaining work worth $900 or less
Contractor's lien expiresEnd of the 60 days after the earlier of published substantial performance or completion (s. 31)End of May 1
Holdback paidWithin 14 days after liens expire (s. 26(8))By May 15

How to release the holdback safely

Release is where homeowners most often slip, usually by paying everything at the final walkthrough because the room looks finished. Follow a short routine instead.

  • Write the trigger into the contract: the completion date (or the date a certificate or declaration of substantial performance is published), the 60-day lien period, then payment.
  • Check for written notices. If a subcontractor or supplier has sent you written notice of a lien, keep enough money back to cover it in addition to the holdback.
  • Search the title. A claim for lien attaches to your property by registration in the land registry office, so a title search, which a real estate lawyer can order, shows whether anything has been registered.
  • Treat late work separately. If work continues after substantial performance, section 22(2) requires a separate 10% finishing holdback on that remaining work.
  • Pause if a lien appears. Do not release the holdback while a lien is registered; get legal advice first.

What changed on January 1, 2026

Amendments to the Construction Act that took effect on January 1, 2026 reworked how holdback is released. The headline change is a mandatory annual release: after each anniversary of the contract date, the owner must publish a notice of annual release of holdback within 14 days and pay the accrued holdback for the previous year 60 to 74 days later, unless a lien has been preserved or perfected. Most kitchen and bathroom renovations finish well inside a year, so the annual release matters mainly for long, phased or whole-house projects. For a typical job, the release still follows the end of the lien period.

What the holdback is not

It is not a deficiency fund, a warranty reserve or leverage in a disagreement. The statutory 10% protects lien claimants; whether you may withhold money for unfinished or defective work is a separate contractual question. Write a deficiency clause into the contract, such as a list signed at the final walkthrough with a date for each fix, and keep any amount tied to it separate from the holdback. See renovation punch lists and deficiencies, and if a disagreement grows, resolving a dispute with a renovation contractor in Ontario.

Questions

Is the holdback the same as a deposit?

No. A deposit is money you pay before work starts. The holdback is money you keep back from each payment as work proceeds, then release after lien rights expire. Your payment schedule should show both.

Does the holdback apply to a small bathroom job?

The obligation attaches to contracts under which a lien may arise, and a bathroom renovation is an improvement under the Act, so size does not remove it. On a $20,000 bathroom, the holdback would be $2,000.

What if my contractor objects to a holdback?

The duty to retain it falls on you as the owner, and it is what limits your exposure to liens from unpaid trades and suppliers. A contractor who asks you to skip it is asking you to carry that risk, which is worth a hard second look.

Does the holdback have to be kept as cash?

For most homeowners, yes, it is simply money not yet paid. The Act also allows a holdback to be retained as a letter of credit or a demand-worded holdback repayment bond in the prescribed form, tools mainly used on larger commercial projects.

Sources and further reading

  1. Construction Act, R.S.O. 1990, c. C.30 (consolidated from January 1, 2026)
  2. Your rights when starting home renovations or repairs, Government of Ontario

Checked November 19, 2026. Codes, by-laws, prices and product specifications change; confirm with your municipality, condo corporation or supplier before you build.

Plan your kitchen renovation

Initial consultations are complimentary. Jordan Duda, our client care and lead estimator, is usually your first point of contact.